3 | Installation Overview

The COMMAND system is to be installed in a structured sequence to ensure correct operation and to minimise installation issues.

Follow the steps below in order. Do not skip steps or complete them out of sequence.

Installation Steps

  1. Complete Pre-Installation Requirements
    Confirm that the tractor, power supply, and components meet system requirements.
  2. Install the ECU
    Select a suitable mounting location and securely install the COMMAND ECU.
  3. Install Cab Components
    Install operator interface components including the arm/engage switch, joystick, and tablet.
  4. Connect Hydraulic Interfaces
    Connect the system to the tractor’s electrohydraulic valves or external valve interfaces.
  5. Install and Configure GNSS and IMU
    Connect and configure the GNSS receiver and IMU as required.
  6. Configure Display and Communication
    Set up NMEA output and ensure communication between system components is functioning correctly.
  7. Verify System Operation
    Perform system checks to confirm correct installation and functionality before operation.

Next Step

Proceed to Section 4 | Pre-Installation.