3 | Installation Overview
The COMMAND system is to be installed in a structured sequence to ensure correct operation and to minimise installation issues.
Follow the steps below in order. Do not skip steps or complete them out of sequence.
Installation Steps
- Complete Pre-Installation Requirements
Confirm that the tractor, power supply, and components meet system requirements. - Install the ECU
Select a suitable mounting location and securely install the COMMAND ECU. - Install Cab Components
Install operator interface components including the arm/engage switch, joystick, and tablet. - Connect Hydraulic Interfaces
Connect the system to the tractor’s electrohydraulic valves or external valve interfaces. - Install and Configure GNSS and IMU
Connect and configure the GNSS receiver and IMU as required. - Configure Display and Communication
Set up NMEA output and ensure communication between system components is functioning correctly. - Verify System Operation
Perform system checks to confirm correct installation and functionality before operation.
Next Step
Proceed to Section 4 | Pre-Installation.