4 | Operator Quick Start

The purpose of this chapter is to guide operators through the basic workflow of using Level COMMAND, from system startup through to performing the first pass safely and confidently.

4.1 | System Startup

When Level COMMAND is first started, the Apply View will be displayed. Before loading a project or attempting to engage Automatic Control, perform the following readiness checks.

image.png

image.png

Verify GNSS Operation

Once the machine is powered on, allow the GNSS receiver(s) several minutes to initialise and obtain RTK corrections.

GNSS status can be checked using either:

If using the Inputs / Offsets page, verify that each configured GNSS receiver displays a Fix Type of RTK before proceeding.

Automatic Control requires RTK-quality positioning for accurate operation. Lower quality fix types such as GPS, Differential GPS or Float RTK may reduce positioning accuracy and automatic control performance. To prevent inaccurate machine control, the COMMAND ECU will not allow Automatic Control to engage unless all required GNSS receivers have achieved an RTK fix.

If RTK fix type has not been achieved after several minutes, common causes include:

Refer to Section 3 | Dealer Installation & Commissioning if GNSS configuration requires adjustment.

image.png

Check COMMAND Status

Once GNSS operation has been verified, review the COMMAND Status indicator shown at the bottom-right of the Apply View.

The COMMAND Status provides information about the current operating state of the system, including whether:

If the system has not previously been configured or commissioned, consult your dealer or refer to Section 3 | Dealer Installation & Commissioning.

Continue to 4.2 | Understanding COMMAND Status for detailed information about the status indicator and its various operating states.

4.2 | Understanding COMMAND Status

image.png

The COMMAND Status area is shown at the bottom-right of the Apply View and provides a quick indication of the current operating state of the COMMAND ECU.

Operators should check COMMAND Status before attempting to engage Automatic Control. The status message indicates whether the system is ready to engage, currently engaged, waiting for an operator action, or unable to operate due to a warning, fault or incomplete setup condition.

Status Colours

The coloured frame around the COMMAND Status area provides a quick visual indication of the current system state:

image.pngimage.pngimage.png

Typical Workflow

Before engaging Automatic Control:

  1. Confirm GNSS has achieved RTK fix.
  2. Confirm the correct project or design surface is loaded.
  3. Check COMMAND Status.
  4. Resolve any warnings or required actions.
  5. Engage Automatic Control only when COMMAND Status shows Ready to Engage.

Green Statuses - Automatic Control Engaged

Green statuses indicate that Automatic Control is currently engaged.

Status Meaning Operator Action
Engaged - Active Automatic Control is engaged and COMMAND may move the implement automatically. Continue operating normally.
Engaged - Low Speed Automatic Control is engaged, but the machine is moving too slowly for COMMAND to move the implement. Increase machine speed above 0.2 km/h to allow automatic implement movement.
Engaged - Calibrating COMMAND is controlling the implement as part of a calibration process. Continue the calibration procedure shown on screen.

Yellow Statuses - Ready for Engagement

Yellow statuses indicate that the system is ready for Automatic Control, but Automatic Control is not currently engaged.

Status Meaning Operator Action
Ready to Engage The system is ready for Automatic Control. Press the engage button when ready to begin.

Red Statuses - Operator Attention Required

Red statuses indicate that operator action, additional setup or fault correction is required before Automatic Control can operate.

Status Meaning Operator Action
Waiting for RTK The GNSS receiver does not have RTK correction yet. Wait for RTK. Check GNSS corrections and receiver setup if RTK is not achieved after several minutes.
No Connection to ECU Level COMMAND cannot communicate with the COMMAND ECU. Check ECU power, wiring and connections.
Blade Width Unset The selected machine profile has not been fully configured. Contact your dealer or complete machine setup before continuing.
Waiting for Manual SCV Input The tractor requires the hydraulic control lever to be moved before Automatic Control can operate. Briefly move the required hydraulic control lever.
System Not Armed Automatic Control has not been armed. Turn the arm/engage switch on, or cycle it off and back on if required.
SCV Locked The tractor hydraulic valve is locked and cannot be controlled by COMMAND. Unlock the required hydraulic valve using the tractor controls.
Speed Too Fast Machine speed is above the maximum allowed Automatic Control speed. Reduce machine speed before engaging Automatic Control.
Waiting for IMU Data COMMAND is not receiving data from the IMU sensor. Check IMU power, wiring and configuration.
Unstable GPS / IMU GNSS or IMU data is changing too quickly or appears invalid. Stop and allow the system to stabilise. Check sensor mounting and signal quality if the warning remains.
NMEA Low Rate GNSS position updates are arriving slower than expected. Check GNSS receiver settings and connections.
T3 Timeout COMMAND has stopped receiving control information from Level COMMAND. Check the tablet, software and ECU connection.
No Active Control Valves No hydraulic valves have been assigned to the active control function. Complete machine setup or contact your dealer.
Check Calibration Hydraulic calibration has not been completed. Complete the calibration process before continuing.
Valve Error A hydraulic valve or valve output has reported an error. Check valve wiring, configuration and hydraulic hardware.
No Main License Level COMMAND is not licensed for operation. Enter a valid software unlock code.
Var Reset Required The ECU requires additional setup after a firmware update. Contact your dealer or T3RRA Support.

Ready to Continue

Once COMMAND Status shows Ready to Engage, the system is ready for Automatic Control engagement.

Continue to 4.3 | Loading or Importing a Project if a project has not yet been loaded, or continue to 4.5 | Engaging Automatic Control if the project and zero reference are already prepared.

4.3 | Loading or Creating a Project

Loading a Design File

To load a design file, press Done at the top-right to return to the Level COMMAND apply page, then press MoreLoad Project. This will open the Change Project page and display all .tad file projects. This file type is specific to LC and the software will automatically scan the file system to find all .tad files present - alternatively to find them manually press "Browse" on the right side of the screen.

Supported design formats:

• T3RRA Project (.tci)
• GPS Design (.gps)
• Existing Level COMMAND Plane Projects

Screenshot 2026-04-27 141149_rounded_r32.png

image.png

image.pngLoading an Existing Level COMMAND Project 

If loading an existing Level COMMAND project (.tad file type), select it from the list and press Load Selected

image.png

Loading an External Design File (Other File Types)

If loading a design of different file type, such as .tci, press "To Import" to move to the Import Data page. Select the design file from the list and then press "Import Selected".

image.png

Creating a Basic Plane Project

A Plane project is the quickest way to begin using Level COMMAND without importing an existing design. Plane projects are commonly used for machine testing, simple levelling work and creating flat pads. To create a basic 2D/3D plane project, begin by pressing More > Start Plane. Choose an appropriate location to save the plane project on the tablet PC and then name the project, then press "Save". 

image.png

image.png

To begin designing a Plane:

  1. Press Planes, then select one of the available Plane slots.
  2. Press Create.
  3. Press Origin and then Use GPS to set the Plane origin to the current implement position.
  4. Press Okay to create a flat Plane surface.

The Plane can now be loaded and used for testing or levelling work.

If a sloped surface is required, press Slope and use Use GPS at a second location to automatically calculate the desired slope.

For detailed information on Plane projects, refer to Section 5 | Operational Workflows

4.4 | Setting Zero

What is Zeroing?

Zeroing aligns the machine to the design surface so that Level COMMAND can guide the implement to the correct elevation.

image.png

A valid zero is required before Automatic Control can operate accurately. If the machine is not correctly zeroed, Level COMMAND may display incorrect cut and fill values and guide the implement to the wrong elevation.

A valid zero should be established whenever:

Different project types may require different zeroing methods. The most common workflows are described below.

Benchmark Markers


image.pngLevel COMMAND separates markers into two categories:

Only Benchmark Markers can be selected when performing a benchmark zero. This helps prevent accidental alignment to an incorrect marker.

Benchmark Markers may be:

Because Plane Origins are stored as Benchmark Markers, they can be used later when re-zeroing a Plane Project.

Zeroing a Plane Project

image.png

Plane Projects are normally zeroed during creation of the Plane itself.

When the Plane Origin is created using Use GPS, the Plane surface is aligned to the current implement position and elevation. If the Primary and Secondary Slopes are also defined using GPS positions, the Plane surface will automatically be aligned to those locations as well.

In most situations no further zeroing is required. However, if the project is reopened later or a different base station is being used, the Plane may need to be re-aligned.

To re-zero a Plane Project:

  1. Position the implement at the Plane Origin.

  2. Place the implement on the ground surface.

  3. Press More → Zero to Benchmark.

  4. Select the Plane Origin marker.

  5. Press Zero.

The Plane Origin will be adjusted to match the current implement position and elevation.

By default, only elevation is adjusted. Latitude and Longitude can also be adjusted if required by disabling the Elevation Only option.

Zeroing a Design with a Benchmark

Many imported designs contain one or more surveyed benchmark locations. A benchmark is a known reference point that can be used to accurately align the machine with the design.

To zero using a benchmark:

  1. Move the machine to the benchmark location.

  2. Place the implement on the benchmark surface.

  3. Press More → Zero to Benchmark.

  4. Select the desired Benchmark Marker.

  5. Press Zero.

image.png

Level COMMAND will record and average approximately 30 seconds of GNSS data before applying the alignment. Once complete, verify that cut and fill values appear reasonable before beginning work.

Zeroing a Design without a Benchmark


If a design does not contain a benchmark, one should be created before beginning work.

Choose a location that:

To create a Benchmark Marker:

  1. Press Marker from the Apply View.

  2. Enter a name such as Benchmark, Bench, BM or MB.

  3. Enable Create Benchmark.

  4. Press Create.

Once the Benchmark Marker has been created, perform the standard benchmark zeroing procedure described above for zeroing a design with a benchmark.

image.png

Zeroing to an Existing Surface (Advanced)

In some situations it may be desirable to align a design to an existing surface rather than a surveyed benchmark.

This method is commonly used when:

Choose an area that:

To align the design:

  1. Position the implement on the chosen location.

  2. Press More → Zero to Benchmark.

  3. Press Offsets.

  4. Press Set Z to Current.

image.png

The design will be shifted vertically so that the current location becomes the new zero reference. Creating a marker at this location is highly recommended so it can be revisited later for verification, or re-zeroed using the Zeroing a Design with a Benchmark process described above.

Ready to Continue

Before engaging Automatic Control, verify that:

✓ A project is loaded.

✓ GNSS receivers have achieved RTK fix.

✓ COMMAND Status shows Ready to Engage.

✓ A valid zero has been established.

Continue to 4.5 | Engaging Automatic Control.

4.5 | Engaging Automatic Control

Before Engaging Automatic Control

Before engaging Automatic Control, verify that:

✓ A project is loaded.

✓ GNSS receivers have achieved RTK fix.

✓ A valid zero has been established.

COMMAND Status displays Ready to Engage.

Ready to Engage indicates that all Level COMMAND and COMMAND ECU requirements have been satisfied and Automatic Control is available for engagement.

If COMMAND Status displays any other message, refer to 4.2 | Understanding COMMAND Status or the Troubleshooting chapter before continuing.

Arming the System

image.png

COMMAND installations use a three-position Arm/Engage switch:

OffArmedEngage (momentary)

The switch must be placed in the Armed position before Automatic Control can be engaged.

If COMMAND Status displays System Not Armed, verify that:

If necessary, cycle the switch to Off and then back to Armed.

Engaging Automatic Control

image.png

Once COMMAND Status displays Ready to Engage, momentarily press the Engage position of the Arm/Engage switch.

COMMAND Status will change to one of the following states:

Engaged - Active

Automatic Control is engaged and COMMAND may actively move the implement to follow the design surface.

Engaged - Low Speed

Automatic Control is engaged, but implement movement is currently disabled because machine speed is below 0.2 km/h.

Once machine speed increases above 0.2 km/h, COMMAND will automatically begin controlling the implement if cut/fill error is present.

Hydraulic Valve Activation

The Engage switch enables Automatic Control within the COMMAND ECU. Depending on the hydraulic system being used, additional tractor or machine controls may also need to be placed into automatic mode.

Common examples include:

If Automatic Control appears to engage correctly but no hydraulic movement occurs, verify that the hydraulic valve system has also been placed into automatic mode.

Disengaging Automatic Control

To disengage Automatic Control, momentarily press the Engage switch again.

COMMAND Status will return to Ready to Engage.

Automatic Control can then be re-engaged at any time by pressing the Engage switch again.

Automatic Disengagement

Automatic Control may automatically disengage if critical operating conditions are no longer satisfied.

Common causes include:

If Automatic Control disengages unexpectedly, check COMMAND Status for additional information.

The last disengagement reason can also be viewed from the Apply View by pressing More → COMMAND Settings → Diagnostics.

Calibration Mode

When performing valve calibration, COMMAND Status may display Engaged - Calibrating.

In this mode, hydraulic movement will only occur while the operator is actively holding the Engage switch during a calibration test.

Releasing the Engage switch immediately stops movement. This behaviour provides an additional level of safety while calibrating hydraulic functions.

What to Expect During First Engagement

When Automatic Control is engaged for the first time:

Observe machine behaviour during the first pass and verify that implement movement matches the expected design direction.

If the implement consistently moves in the wrong direction, disengage Automatic Control immediately. The hydraulic valve extend/retract direction may need to be corrected using Swap Extend/Retract from More → COMMAND Settings → Valve Cals. Refer to the commissioning or troubleshooting sections if unsure.

Ready to Continue

Once Automatic Control can be engaged successfully and the implement responds correctly, continue to 4.6 | Performing Your First Pass.

4.6 | Performing Your First Pass

Understanding the Operator's Role

Level COMMAND automatically controls the implement to follow the selected design surface, but it does not decide where material should be moved from or where it should be placed.

The operator remains responsible for planning the earthmoving operation, including:

Careful planning can significantly improve productivity by reducing unnecessary material movement and minimising rework. Material that is moved multiple times before reaching its final location increases both operating time and fuel consumption.

Monitoring Automatic Control

Once Automatic Control is engaged, monitor the Apply View to verify that COMMAND is operating as expected.

image.png

Important indicators include:

Error Chevron

The Error Chevron indicates whether the implement is above or below the design surface. As Automatic Control operates, the Error Chevron should generally move toward zero as the design elevation is approached.

Cross Section View

If using both Height and X-Slope control, monitor the Cross Section View to verify that both elevation and cross-fall are tracking correctly.

Cut/Fill Information

Monitor upcoming cut and fill values to understand how much material is approaching. Large cut or fill values may require a different operating strategy than smaller corrections.

Understanding the Control Profile

image.pngThe Control Profile provides a visual representation of the current Automatic Control target and implement position.

To display the Control Profile, press Blade Shift from the Apply View. The Control Profile will appear on the right side of the screen.

The profile displays:

Original

The original surveyed surface elevation.

Target

The elevation that Automatic Control is currently attempting to achieve.

Design

The final design elevation.

Current

The current measured implement elevation.

As Automatic Control operates, the Current position should generally move toward the Target position.

If Dynamic Cut Limit or Dynamic Fill Limit is active, the Target position may intentionally differ from the Design elevation. The shaded area of the Control Profile indicates material that will not be cut or filled during the current pass.

Using Blade Shift

image.png

Blade Shift allows the operator to temporarily raise or lower the Automatic Control target without modifying the underlying design surface.

Use the Up and Down buttons to adjust the shift value.

Common uses include:

Blade Shift affects Automatic Control behaviour only and does not modify the design file.

Using Cut/Fill Limit

image.png

Cut/Fill Limiting allows Automatic Control to progressively work toward the design surface over multiple passes.

To access Cut/Fill Limiting:

  1. Press Blade Shift.

  2. Press Blade Limit.

  3. Enable Dynamic Cut Limit and/or Dynamic Fill Limit.

  4. Enter the desired limit value.

For example:

A Dynamic Cut Limit of 0.05 m will cause Automatic Control to target only 5 cm of cut during each pass, even if the full design requires a larger cut.

This can assist with:

Multiple passes may be required to reach final grade when Cut/Fill Limiting is enabled.

Changing Surface Display Modes

Different map layers can be displayed depending on the information required.

Display settings can be changed from:

More → Appearance

Common display modes include:

image.png

Design

Displays the intended finished design surface.


image.pngAs Elevation

Displays the measured surface elevation collected during operation.


image.pngAs Cut/Fill

Displays current cut and fill values based on the latest surveyed surface.

The As Elevation and As Cut/Fill layers update dynamically as work progresses, making them useful for monitoring grading performance during operation.

Signs That Automatic Control Is Working Correctly

During normal operation:

If Performance Appears Incorrect

If the implement appears slow to respond, struggles to reach grade or behaves erratically, verify that commissioning and calibration have been completed correctly.

Common causes include:

Tracking Sensitivity controls the overall aggressiveness of Automatic Control:

If required, adjust Tracking Sensitivity in small increments and observe the resulting behaviour.

Verifying the Completed Pass

Once a pass has been completed, inspect both the worked surface and the map display. The completed area should generally show reduced cut/fill values and move closer to on-grade conditions. Multiple passes may be required where large cut or fill values are present.

In some situations, manual intervention may still be required to relocate material efficiently between cut and fill areas.

Confirming Surface Accuracy

Inspect the completed surface and check for:

If concerns remain about the accuracy of the completed work, a survey may be performed and compared against the updated surface displayed within Level COMMAND.

Ready to Continue

Once Automatic Control is producing smooth implement movement and the completed surface matches expectations, continue operating normally.

Refer to Chapter 5 for additional operational workflows and Chapter 6 for detailed information on Automatic Control behaviour. Continue on to 4.7 | Closing Level COMMAND.

4.7 | Closing Level COMMAND

Before Closing Level COMMAND

Before closing Level COMMAND, verify that:

✓ Automatic Control has been disengaged.

✓ Hydraulic functions have been returned to manual operation.

✓ The machine is in a safe operating condition.

✓ The implement has been lowered safely to the ground where appropriate.

If COMMAND Status shows Engaged - Active or Engaged - Low Speed, disengage Automatic Control before continuing.

Saving Your Work

Projects, design files, Plane surfaces, markers and configuration changes are saved automatically as they are created or modified. In normal operation, no manual save process is required before exiting Level COMMAND.

Although work is saved automatically, it is good practice to close Level COMMAND before shutting down the tablet or PC.

If you wish to manually save a copy of the current project:

  1. Press More.
  2. Press the current project name at the top of the window.
  3. Press Save As.
  4. Select the desired save location.
  5. Press Save.

image.png

image.png

This can be useful when creating backups, archiving completed projects or creating a modified copy of an existing project.

Closing the Application

image.png

To close Level COMMAND:

  1. Press More.

  2. Press Close App at the bottom right.

  3. Press Yes.

The application will close and return to the operating system.

Automatic Startup

Level COMMAND can be configured to start automatically when Windows starts.

To modify this setting:

More → Diagnostics/Advanced

Use the Start Level COMMAND when computer starts option to enable or disable automatic startup. This setting is enabled by default.

image.png

Unexpected Shutdowns

If the tablet or PC unexpectedly shuts down, COMMAND will automatically disengage Automatic Control once position updates are no longer received from Level COMMAND.

The operator immediately becomes responsible for machine control and implement position.

If an unexpected shutdown occurs:

Because project information is saved automatically, work progress will normally be retained after restarting the application.

Restarting Level COMMAND

When Level COMMAND is started again:

Automatic Control will not automatically re-engage after restarting the application. The operator must verify system readiness and manually engage Automatic Control before continuing work.

Quick Start Complete

You have now completed the basic Level COMMAND Quick Start workflow:

  1. Start Level COMMAND.

  2. Check COMMAND Status.

  3. Load or create a project.

  4. Set Zero.

  5. Engage Automatic Control.

  6. Perform a pass.

  7. Exit Level COMMAND safely.

For additional workflows, project creation tools and advanced operating procedures, continue to Chapter 5 | Operational Workflows.